Burlington Electric Department RFP System
RFP# 025-25 ESP Field Rebuild
RFP# 025-25
Deadline: January 28, 2025 11:00 am
RFP# 025-25 ESP Field Rebuild
Burlington Electric Department, a Local Government Agency would like to receive one-fixed cost
proposal for the rebuild of one Electrostatic Precipitator field per the scope below.
Please submit your proposal to provide materials and labor during the two-week planned outage for
maintenance work on the electrostatic precipitator at the McNeil Generating Station in accordance with
the following specifications by January 24, 2025.
• Facility Description - The McNeil Generating Station is a 50 MWe steam driven wood fired
electric generating station located in the City of Burlington, Vermont. To comply with air
quality standards, the Station operates an electrostatic precipitator (ESP) when firing wood.
The ESP is a GEESI (Buell) Model BA1.2x52K4443-6.4P with 30' plates. (See BED Figure 2 for
the plan outline and terminology to be used.) The collecting plates and emitting wires were
replaced in 1997 by BHA. The BHA drawings show what was installed and need to be replaced
in this project.
• Contractor's Supply - The Contractor shall supply both materials and installation labor with
supervision for the outage work specified below. The Contractor shall provide approved
drawings of all materials to be installed no later than six (6) weeks prior to delivery of the
materials.
Documents
Submit Your Proposal